Weather permitting, Georgia Department of Transportation (Georgia DOT) construction partners will close interstate lanes at the locations below for the 16@95 Improvement Projects, which will widen I-16 and reconstruct the I-16/I-95 Interchange. The lane closures are necessary for widening activities for I-16, bridge work on I-95, and bridge work at the I-16/I-516 Interchange. For daily traffic impacts and real-time traffic alerts, please visit Georgia NaviGAtor at www.511ga.org.
NOTE: Detour information is shown in red text.
Daytime Closures
Monday, December 5, through Saturday, December 10, 8 a.m. to 3 p.m.
Intermittent right and left lane closures at the following locations
- I-16 westbound from the I-16/I-516 Interchange (MP 164) to the I-16/I-95 Interchange (MP 157)
Monday, December 5, through Saturday, December 10, 9 a.m. to 4 p.m.
Intermittent right and left lane closures at the following locations
- I-16 eastbound from the I-16/I-95 Interchange (MP 157) to I-16/I-516 Interchange (MP 164)
Monday, December 5, through Saturday, December 10, 8 a.m. to 5 p.m.
Intermittent right and left lane closures at the following locations
- I-516 westbound at the I-16 Interchange from MP 5 to MP 6
- I-516 eastbound at the I-16 Interchange from MP 6 to MP 5
Overnight Closures
Monday, December 5, through Saturday, December 10, 7 p.m. to 6 a.m.
Intermittent right and left lane closures at the following locations
- I-16 westbound from the I-16/I-516 Interchange (MP 164) to the I-16/I-95 Interchange (MP 157)
- I-16 eastbound from the I-16/I-95 Interchange (MP 157) to the I-16/I-516 Interchange (MP 164)
Monday, December 5, through Saturday, December 10, 9 p.m. to 5 a.m.
Double lane closures at the following locations
- I-95 northbound @ I-16 overpass (MP 98 to MP 100)
- I-95 southbound @ I-16 overpass (MP 101 to MP 98)
Continuous Closure
Friday, December 2, through Monday, December 5, 7 p.m. to 5 a.m.
Right lane closures at the following locations
- I-95 northbound @ I-16 overpass (MP 98 to MP 100)
- I-95 southbound @ I-16 overpass (MP 101 to MP 98)
Friday, December 9, through Monday, December 12, 7 p.m. to 5 a.m.
Right lane closures at the following locations
- I-95 northbound @ I-16 overpass (MP 98 to MP 100)
- I-95 southbound @ I-16 overpass (MP 101 to MP 98)
Overnight Closures with Detours
*Ramp closures will not occur concurrently with one another or with the continuous lane closures on I-95.
Monday, December 5, to Saturday, December 10, 10 p.m. to 5 a.m. (Nightly)
- I-95 northbound to I-16 eastbound ramp (Exit 99A) (Map)
Motorists traveling on I-95 northbound should continue past the I-16/I-95 Interchange, exit at US Hwy 80 (Exit 102) turn left off the ramp, then turn left to access I-95 southbound, then take the I-16 eastbound ramp (Exit 99A).
Monday, December 5, to Saturday, December 10, 10 p.m. to 5 a.m. (Nightly)
- I-95 southbound to I-16 westbound ramp (Exit 99B) (Map)
Motorists traveling on I-95 southbound should continue past the I-16/I-95 Interchange, exit at SR 204 (Exit 94) turn left off the ramp, then turn left to access I-95 northbound, then take the I-16 westbound ramp (Exit 99B).
Long-Term Closure
June 2, 2022, through May 31, 2023
- Tremont Road under I-16 (Map)
Note: Tremont Road will be open during holiday work restriction time frames.
- Motorists traveling on Tremont Road north of I-16 should take Telfair Road northbound, turn right on West Gwinnett Street, turn right onto I-516 eastbound, then exit at Tremont Road (Exit 4)
- Motorists traveling on Tremont Road south of I-16 should take I-516 westbound to West Gwinnett Street (Exit 6), turn left on West Gwinnett Street, then left on Telfair Road to access Tremont Road north of I-16