Northwest Georgia: Monthly Project Update
Bartow County
- Old Alabama Road Widening: The project is about 43% complete. Current Completion Date: End of 2024.
- Cassville-White Road Roundabout Construction: The project is approximately 62% complete. Crews continue to build the roundabouts as well as new interstate ramps. Current Completion Date: Spring 2024.
- Highway 41 Bridge Construction over State Route 293 and CSX railroad in Emerson: Work is just beginning. Current Completion Date: End of 2025.
Cherokee County
- SR 20 Widening of I-575 to Scott Road: Approximately 90% complete. Crews are working on medians, sidewalks, and signals. Completion Date: Fall 2023.
- SR 20 Widening from Scott Road to Union Hill Road: Approximately 42% complete. Current Completion Date: End of 2024.
Gordon and Bartow County
- Resurfacing I-75 from US 411 to Dews Pond Road overpass: Approximately 9% complete. Current Completion Date: Early 2024.
Fannin County
- Bridge construction on SR 60 over Hothouse Creek: 40% complete. Grading continues. Current Completion Date: Spring 2024.
Buchanan \and Carroll County
- Roundabout construction on SR 16 at Columbia Drive and Brumbelow Road: 5% complete. Current Completion Date: Late 2024.
Haralson County
- Roundabout construction at Waco Road and I-20 interchanges: 84% complete. Current Completion Date::
Carroll County
- Bridge construction on US 27 over Little Tallapoosa River: 31% complete. Current Completion Date: Summer 2024.
- Villa Rica Bypass from SR 101 to SR 61: 18% complete. Current Completion Date: Late 2025.
Cobb and Paulding County
- SR 92 widening from Old Burnt Hickory Road to US 41: 20% complete. Storm drain and basin installation. Expected Completion Date: Spring 2026.
Douglas and Paulding County
- SR 92 widening from Malone Road to Nebo Road: 68% complete. Current Completion Date: Fall 2024.
Polk County
- Bridge construction on SR 101 over Euharlee Creek Tributary: 27% complete. Preparing to install main water pipe. Current Completion Date: Summer 2024.
Chattooga County
- Bridge construction on SR 48 over Raccoon Creek: 34% complete. Current Completion Date: Summer 2024.
Floyd County
- Bridge construction on SR 293 over Dykes Creek: 8% complete. Current Completion Date: Late 2025.
- Resurfacing SR 20 from SR 100 to SR 1: 4% complete. Current Completion Date: Late 2023.
Walker County
- Bridge construction on US 27 over West Chickamauga Creek: 78% complete. Current Completion Date: Late 2023.
- Bridge construction on Old Trion Highway over Old Dry Creek: 79% complete. Current Completion Date: Late 2023.
Related Topics
Click to comment
Chattooga Schools
Berry Professor Publishes Original Short Story Collection
Chattooga Public Safety
Most Recent Chattooga County Food Service Inspections
Chattooga Schools
GNTC names 2026 GOAL, Rick Perkins Award winners
Chattooga Local News
When Summerville Needed Him, Kevin Godfrey Showed Up — Again
Bulloch Public Safety
01/20/2026 Booking Report for Bulloch County
Bulloch Public Safety
01/12/2026 Booking Report for Bulloch County
Bulloch Public Safety
01/09/2026 Booking Report for Bulloch County
Bulloch Public Safety
01/26/2026 Booking Report for Bulloch County
Bulloch Public Safety
01/05/2026 Booking Report for Bulloch County