Final Module Placed for Vogtle Unit 3

The final module for Georgia Power’s Vogtle Unit 3, a massive water tank, has been placed atop the containment vessel and shield building roof at the company’s Vogtle 3 & 4 nuclear expansion project near Waynesboro, Georgia.

720,000-pound water tank is a major part of unit’s advanced safety system
The final module for Georgia Power’s Vogtle Unit 3, a massive water tank, has been placed atop the containment vessel and shield building roof at the company’s Vogtle 3 & 4 nuclear expansion project near Waynesboro, Georgia. The installation represents the final module placement for Unit 3, marking another significant milestone for the project.

The large module, known as CB-20, is a major part of the AP1000 reactor’s advanced passive safety system. Standing 35 feet tall and weighing more than 720,000 pounds, the large component will hold approximately 750,000 gallons of water ready to flow down in the unlikely event of an emergency to help cool the reactor. The water can also be directed into the used fuel pool, while the tank itself can be refilled from water stored elsewhere on site.

The AP1000 plant’s passive safety systems require no operator actions to mitigate potential emergency situations. These systems use only natural forces such as gravity, natural circulation and compressed gas to achieve their safety function. No pumps, fans, diesels, chillers or other active machinery are used, except for a few simple valves that automatically align and actuate the passive safety systems.

The modules used for Vogtle units 3 & 4 help streamline the construction process, since they were made in advance of arriving to the project site and ready to be assembled into larger components that make up the nuclear units. Since 2011, major modules have been delivered to the site by rail and truck, and included a range of plant components such as floor and wall sections and supporting structures that surround the containment buildings and reactor vessels. The final major module arrived at the construction site in late 2019, meaning all 1,485 major modules required to complete construction had been manufactured and safely delivered.

Key Milestones
The placement of the CB-20 module follows the placement of the Unit 3 integrated head package (IHP) atop the reactor vessel. Standing 48 feet tall, weighing 475,000 pounds and containing more than three miles of electrical cables, the IHP is an integral component that will eventually be used by highly-trained nuclear operators to monitor and control the nuclear reaction that will occur inside the Unit 3 reactor vessel.

Additional milestones achieved over the last few months include:

  • Completion of Open Vessel Testing for Unit 3 – This successfully demonstrated how water flows from the key safety systems into the reactor vessel ensuring the paths are not blocked or constricted, and confirmed the pumps, motors, valves, pipes and other components of the systems function as designed.
  • Placement of the polar crane and containment vessel top for Unit 4 – This signifies that all major lifts inside the containment vessels for both units are now complete.
  • Operation of the Unit 3 main control room – Operators begin monitoring and controlling the technology and equipment essential for testing the unit’s systems and safely starting the plant.
  • Placement of the Unit 3 shield building roof – The two-million-pound roof covers the top of the shield building, which provides an additional layer of safety around the containment vessel and nuclear reactor to protect the structure from any potential impacts.
  • Final concrete placement inside the Unit 3 containment vessel – Completing this milestone is an important step that allows for the installation of machinery that will be used to load fuel into the unit.

Historic milestones accomplished over the past year include:

  • Ordering the first nuclear fuel loads for both units 3 & 4. Consisting of 157 fuel assemblies with each measuring 14 feet tall, the fuel will eventually be loaded into the reactor vessels to support startup once the reactors begin operating.
  • Placing the containment vessel top heads for both units, marking that the project’s final major lifts inside the containment vessels are complete. The containment vessel is a high-integrity steel structure that houses critical plant components.
  • Completing the first emergency preparedness drill for the new units, which includes a comprehensive review of the site’s plans to ensure the protection of the public. The emergency preparedness plan specifies the response actions if the site were ever to experience an incident.
  • Finalizing Department of Energy (DOE) loan guarantees for the Vogtle 3 & 4 project. Through the company’s $5.13 billion loan guarantee capacity with the DOE, Georgia Power customers are expected to save approximately $550 million in financing costs overall.
  • Completing the multi-year training necessary for the nuclear operators required for the new units, which culminated with the Nuclear Regulatory Commission (NRC) license exam. From the main control room, operators will monitor and control the technology and equipment essential for testing the unit’s systems and safely starting the plant.

With more than 7,000 workers on site, and more than 800 permanent jobs available once the units begin operating, Vogtle 3 & 4 is currently the largest jobs-producing construction project in the state of Georgia.

This is a press release from GeorgiaPower.